5th Generation GPON ONT introduction
We're introducing a new 5th Gen GPON ONT (model type 500) that will become our new standard ONT for core NGA connections
Overview
We have received an ‘end of sale’ notice from Nokia for the type 400 GPON ONT as its manufacture will soon cease. We have placed a final order which is forecast to meet demand up to November 2025. This new 5th Gen GPON ONT (model Type 500) will become our new standard ONT for core NGA connections.
The type 500 ONT will ensure customers can continue to enjoy the benefits of fibre connectivity well after the type 400 ONT is no longer available.
We expect the new 5th Gen GPON ONT to be largely similar in functionality to the current 4th Gen ONT except it will not need the external Wi-Fi antenna as RGW ONT will be fully withdrawn on 31 October 2024. Consultation workshops with service providers to discuss requirements will help shape the form and function of the new ONT.
Quick find
Timeline and approach
26 June 2024
Consultation opens
Consultation is open until 24 October 2024. Please provide feedback via our feedback form or contact your account team to arrange a meeting to discuss further.
23/24 July 2024
RSP Workshop 1
Chorus intends to run workshops to keep you up to date on how we progress through this project. These will cover your feedback, ONT capabilities, rollout plan, testing, mounting and the customer experience, etc.
October 2024
ONT test plan provided to RSPs
Chorus will provide the test plan for the new ONT.
October 2024
RSP Workshop 2
Chorus present the selected ONT model based on requirements and feedback.
24 October 2024
Consultation closes
Consultation closes and feedback will be provided.
October 2024
Notice of LFC Equipment Change
Notice of LFC Equipment Change
Mid 2025
RSP testing
Confirmation with RSPs to confirm that you are ready for the 5th Gen ONT to start being installed.
November 2025
Proposed launch of 5th Gen GPON ONT
Large scale deployment of 5th Gen ONT expected to commence.
What’s next
What’s next
Consultation begins with a feedback form and workshops in which we will work through feedback, requirements and ONT selection.
Frequently asked questions
Get updates on our inflight projects
Check your subscriptions settings and ensure you’ve
got innovation projects activated.
Check subscriptions
More change initiatives View All
01/03/2023
Copper withdrawal in fibre areas
17/05/2022