5th Generation GPON ONT introduction

We're introducing a new 5th Gen GPON ONT (model type 500) that will become our new standard ONT for core NGA connections

Overview

We have received an ‘end of sale’ notice from Nokia for the type 400 GPON ONT as its manufacture will soon cease. We have placed a final order which is forecast to meet demand up to November 2025. This new 5th Gen GPON ONT (model Type 500) will become our new standard ONT for core NGA connections.

The type 500 ONT will ensure customers can continue to enjoy the benefits of fibre connectivity well after the type 400 ONT is no longer available.    ​

We can now confirm that the new 5th Gen GPON ONT is the Zyxel PX5301.

5th Gen GPON ONT

Timeline and approach

Consultations on the new ONTs took place near the end of 2024, during which we gathered and discussed your feedback.​

RSP ONT Testing will begin in May 2025 and run through to launch.​ Current forecasts put our launch in July 2025.

26 June 2024

Consultation opens

Consultation is open until 24 October 2024. Please provide feedback via our feedback form or contact your account team to arrange a meeting to discuss further.

23/24 July 2024

RSP Workshop 1

Chorus intends to run workshops to keep you up to date on how we progress through this project. These will cover your feedback, ONT capabilities, rollout plan, testing, mounting and the customer experience, etc.

October 2024

ONT test plan provided to RSPs

Chorus will provide the test plan for the new ONT.

October 2024

RSP Workshop 2

Chorus present the selected ONT model based on requirements and feedback.

24 October 2024

Consultation closes

Consultation closes and feedback will be provided.

October 2024

Notice of LFC Equipment Change

Notice of LFC Equipment Change

Feb 2025​

Label design workshop​

Chorus workshop to look at the design of the labels for the new ONTs.​

Mar 2025​

Select a new ONT​

2025​

Service company training​

Documentation updated and training rolled out to service companies on the new ONT.​

May 2025​

RSP testing via CCIL lab​

RSPs will be able to test the new ONT on the correct software version in CCIL and labs.​

Mid 2025​

RSP readiness check​

Confirmation with RSPs that you are ready for the 2nd Gen XGS (Hyperfibre) ONT to start being installed in the production network.​

Jul 2025​

Expected introduction of 5th Gen GPON ONT

Large scale deployment of 5th Gen ONT expected to commence.

What’s next

What’s next

What’s next

Consultation begins with a feedback form and workshops in which we will work through feedback, requirements and ONT selection.

Frequently asked questions