2nd Generation XGS (Hyperfibre) ONT Introduction

We're introducing a new 2nd gen XGS (Hyperfibre) ONT to replace the current ONT that was introduced in late 2019.

Overview

We have been working through the preproduction steps associated with the introduction of the new 2nd Gen Hyperfibre ONT.

Regrettably, we must inform you that the launch has been delayed by three to six months. This decision was made due to unresolvable issues uncovered during our testing process, preventing the new ONT from meeting our product requirements. We understand the inconvenience this may cause and sincerely apologise for any disruption to your plans.

Timeline and next steps

We will confirm the timeline once a new ONT has been selected.

14 April to 14 July 2022

RSP consultation process and Impact assessment

RSP workshops to discuss Capabilities of the ONT, rollout plan, testing, mounting and the customer experience, etc. Industry feedback gathered.

Sep 2022

Notice to implement change given

Formal notice of new LFC hardware introduction issued.

Early 2024

Select a new ONT

Late 2024

2nd Gen XGS (Hyperfibre) ONT test plans provided to RSPs

Chorus test plans provided to the industry through the TCF Forum.

Late 2024

Service company training

Documentation will be updated and training rolled out to service companies on the new ONT.

Late 2024

RSP testing via CCIL lab

RSPs will be able to test the new ONT on the correct software version in CCIL and labs.

Early 2025

RSP readiness check

Confirmation with RSPs that you are ready for the 2nd Gen XGS (Hyperfibre) ONT to start being installed in the production network.

Early 2025

Proposed launch of 2nd Gen XGS (Hyperfibre) ONT

Stock of 1st Gen XGS ONT forecast to run out. Introduction of the 2nd Gen XGS ONT.

RSP Consultations were held from 14 April to 14 July 2022, in which we discussed topics like ONT capabilities, supported services and form factor, to gather feedback on what is important to you, our customers.

Test plans for the new ONT will be shared through the TCF Forum.
Test ONTs will be sent out to RSPs when the stock and final version of the software have arrived.
 

Frequently asked questions