Wireless Colocation

Service Levels

Service levels

Wireless Colocation tasks (single site)Target time frames (working days)
Stage 1 - Site Data Pack request (Optional)3 days
SP submits Site Data Pack Application0 days
Chorus issues Site Data Pack3 days
Stage 2 - Site Visit (Optional)13 days
SP requests site visit0 days
Chorus assesses the request and ensures all relevant accreditation provided3 days
Chorus arrange accreditation training for SP representatives (if applicable)N/A
Chorus and SP arrange escorted Site Visit (if applicable)10 days
Stage 3 – Full Site Application13 days
SP submits Full Site Application0 days
Chorus confirms Full Site Application valid3 days
Chorus issues Preliminary Site Approval or rejects with reasons10 days
Stage 4 - Landlord/Third Party Approvals, RMA consents and Final Site Approval93 days
Chorus issues Preliminary Site Approval0 days
Chorus requests approval from third parties and landowner5 days
Chorus notifies customer consent gained or schedules meeting to discuss next steps20 days
SP obtains RMA consents and any other condition outlined in Prelim approval letter90 days
SP provides Preliminary Notice to Chorus that all conditions in Preliminary Site Approval fulfilled0 days
Chorus confirms Preliminary Notice received, Chorus issues Final Site Approval or rejects with reasons3 days
Stage 5 - Approval to Build10 days
SP submits Project Plan0 days
Chorus reviews Project Plan, approves Project Plan and issues Approval to Build or requests changes to Project Plan if required10 days
Stage 5 - Commercial Wireless Colocation Site Build20 days
Commercial Wireless Colocation Build PeriodN/A
Project Closure20 days
Planned Work13 days
SP Submits Planned work request0 days
Chorus assesses the request and advises if a planned work request is required and whether the request has enough information3 days
Chorus notify SP if planned work approved10 days

Please note that operations manual changes were introduced in March 2018: 

  • Application process changes
    • Site Data Pack timeframe reduced from 5 to 3 days
    • Full Site Application timeframe reduced from 20 to 13 days
    • Preliminary Acceptance timeframe reduced from 5 to 3 days
    • Planned Work timeframe increased from 5 to 13 days
  • All work outside customer space within Chorus Exchanges is now undertaken by Chorus
  • Capital Cost Contribution process for Unplanned Maintenance
  • Power standards updated
  • Third party and landowner approval process updated
  • Access Tracks updated
  • Planned Work requirements updated
  • Health and Safety updated