Fibre network extension

To ensure more of New Zealand can run on fibre, we’re extending our fibre network to give 10,000 more Kiwi homes and businesses access to fibre services

Overview

Keep up to date with progress on our large scalefibre build programme including when you’ll be able to make the most of new connect opportunities.

The new build programme began in mid-February 2024 with civil works finishing in July 2025 and the final premises in the programme expected to be ready for service by October 2025.

It has seen fibre rolled out to 59 communities across New Zealand in locations adjacent to urban areas or close to the existing Chorus network, from Kerikeri in the north to Winton in the south.

The below table outlines the ready for service dates in each location along with number of premises. Please note the dates are indicative and may be subject to change.

 

Exchange Name

Area

Premises

Build Start

RFS Date

Okere Falls

Otaramarae

118

19/02/2024

17/06/2024

Kerikeri

KC Fringe 1

90

26/02/2024

30/06/2024

Waiau Pa

Waiau Pa

132

12/02/2024

30/06/2024

Upper Hutt North

Mangaroa

54

15/04/2024

31/07/2024

Atawhai

AWI North

161

11/03/2024

19/08/2024

Kawakawa

Moerewa East

53

13/05/2024

31/08/2024

Brighton

Westwood

71

6/05/2024

2/09/2024

Glentunnel

Whitecliffs

131

19/02/2024

2/09/2024

Hastings

Karamu

105

15/07/2024

15/10/2024

Kaeo

Kaeo

114

1/07/2024

13/11/2024

Kaipara Flats

Kaipara Flats

66

2/09/2024

29/11/2024

Tairua

Lakes Resort Golf Club Pauanui

176

15/07/2024

29/11/2024

Winton

Winton fringe

19

7/10/2024

29/11/2024

Karaka

Kingseat

64

2/09/2024

13/12/2024

Urenui

Onaero Beach

78

22/07/2024

13/01/2025

Whitianga

Whitianga

156

26/08/2024

28/01/2025

Kaharoa

Awahou

86

12/08/2024

10/02/2025

Kaiapoi

Kairaki

153

5/08/2024

17/02/2025

Diamond Harbour

Purau

74

28/10/2024

28/02/2025

Waikanae

Waikanae North

56

4/11/2024

6/03/2025

French Pass

Okiwi Bay

206

9/09/2024

31/03/2025

Leigh

Whangateau

73

14/10/2024

31/03/2025

Onerahi

Pataua

209

23/09/2024

31/03/2025

Glenbrook

Glenbrook Beach

139

28/10/2024

30/04/2025

Kaharoa

Unsworth Rd Hamurana

58

5/08/2024

30/04/2025

Otautau

Otautau Sth

73

4/11/2024

30/04/2025

Ohakune

Rangataua

219

30/09/2024

30/04/2025

Te Anau

Milford

54

2/09/2024

30/04/2025

Kaharoa

Hamurana

529

2/09/2024

31/05/2025*

Kaharoa

Gloucester Rd

57

7/10/2024

3/06/2025

Kerepehi

Kerepehi

231

19/08/2024

3/06/2025

Levin

Levin UFB1 Fringe

76

20/01/2025

3/06/2025

Tahuna

Tahuna

62

24/02/2025

3/06/2025

Whitianga

Kuaotuna West

142

2/12/2024

3/06/2025

Blenheim

Dry Hills Fringe

80

20/01/2025

6/06/2025

Fielding

Fielding UFB1 Fringe

61

10/03/2025

6/06/2025

Lyttelton

Cass Bay

286

18/11/2024

14/08/2025

Mangakino

Whakamaru

113

17/02/2025

30/06/2025

Matakana

Million Bay

163

9/12/2024

30/06/2025

Diamond Harbour

Charteris Bay

282

2/12/2024

8/09/2025

Huia

Cornwallis

74

24/03/2025

31/07/2025

Havelock North

UFB Fringe East

347

5/08/2024

31/07/2025

Lynmore

Te Ngae

272

24/02/2025

22/09/2025

Otatara

SW Otatara

95

24/02/2025

31/07/2025

Paparoa

Tinopai

253

13/01/2025

31/07/2025

Puketurua

Arapuni

172

13/01/2025

8/09/2025

Rotoiti

Rotoiti 2

194

24/03/2025

31/07/2025

Taradale

Breckenridge Rd

102

4/11/2024

21/08/2025

Waitakere

Waitakere Fringe South

196

17/02/2025

14/08/2025

Whangamata

Whiritoa

573

13/01/2025

21/08/2025

Whangamata

Oputere

102

21/04/2025

14/08/2025

Hastings

Pakipaki

42

16/09/2024

15/09/2025

Okere Falls

Mourea

218

21/04/2025

22/09/2025

Onerahi

Parua Bay

285

10/02/2025

15/09/2025

Rotoma

Rotoma

241

24/02/2025

8/09/2025

Rotoma

Pongakawa Valley Road

89

31/03/2025

15/09/2025

Tapu

Te Mata

201

10/03/2025

22/09/2025

Taupo

Waitahanui

233

17/03/2025

8/09/2025

Whangamata

Onemana

381

31/03/2025

15/09/2025

What's next

The above table will be updated as the programme progresses and we will notify you when this happens as part of the standard service provider communications email update process. 

To receive address lists for premises that will be ready for connect soon, please contact your Chorus account team.

Keep up to date with the Chorus fibre network extension.