Fibre network extension

To ensure more of New Zealand can run on fibre, we’re extending our fibre network to give 10,000 more Kiwi homes and businesses access to fibre services

Overview

Keep up to date with progress on the new build programme including when you’ll be able to make the most of new connect opportunities.

The new build programme began in mid-February 2024 and is expected to take 18 months to complete.

It sees fibre rolled out to 59 communities across New Zealand in locations adjacent to urban areas or close to the existing Chorus network, from Kerikeri in the north to Winton in the south.

The below table outlines when the next locations in the programme should be ready for service. Please note the dates are indicative and may be subject to change. 

Exchange NameAreaPremisesBuild StartRFS Date
Okere FallsOtaramarae11819/02/202417/06/2024
KerikeriKC Fringe 19026/02/202430/06/2024
Waiau PaWaiau Pa13212/02/202430/06/2024
Upper Hutt NorthMangaroa5415/04/202431/07/2024
AtawhaiAWI North16111/03/202419/08/2024
KawakawaMoerewa East5313/05/202431/08/2024
BrightonWestwood716/05/20242/09/2024
GlentunnelWhitecliffs13119/02/20242/09/2024
HastingsKaramu10515/07/202415/10/2024
KaeoKaeo1141/07/202413/11/2024
Kaipara FlatsKaipara Flats662/09/202429/11/2024
TairuaLakes Resort Golf Club Pauanui17615/07/202429/11/2024
WintonWinton fringe197/10/202429/11/2024
KarakaKingseat642/09/202413/12/2024
UrenuiOnaero Beach7822/07/202413/01/2025
WhitiangaWhitianga15626/08/202428/01/2025
KaharoaAwahou8612/08/202410/02/2025
KaiapoiKairaki1535/08/202417/02/2025
Diamond HarbourPurau7428/10/202428/02/2025
WaikanaeWaikanae North564/11/20246/03/2025
French PassOkiwi Bay2069/09/202431/03/2025
LeighWhangateau7314/10/202431/03/2025
OnerahiPataua20923/09/202431/03/2025
GlenbrookGlenbrook Beach13928/10/202430/04/2025
KaharoaUnsworth Rd Hamurana585/08/202430/04/2025
OtautauOtautau Sth734/11/202430/04/2025
OhakuneRangataua21930/09/202430/04/2025
Te AnauMilford542/09/202430/04/2025
KaharoaHamurana5292/09/202431/05/2025*
KaharoaGloucester Rd577/10/20243/06/2025
KerepehiKerepehi23119/08/20243/06/2025
LevinLevin UFB1 Fringe7620/01/20253/06/2025
TahunaTahuna6224/02/20253/06/2025
WhitiangaKuaotuna West1422/12/20243/06/2025
BlenheimDry Hills Fringe8020/01/20256/06/2025
FieldingFielding UFB1 Fringe6110/03/20256/06/2025
LytteltonCass Bay28618/11/202430/06/2025
MangakinoWhakamaru11317/02/202530/06/2025
MatakanaMillion Bay1639/12/202430/06/2025
Diamond HarbourCharteris Bay2822/12/202431/07/2025
HuiaCornwallis7424/03/202531/07/2025
Havelock NorthUFB Fringe East3475/08/202431/07/2025
LynmoreTe Ngae27224/02/202531/07/2025
OtataraSW Otatara9524/02/202531/07/2025
PaparoaTinopai25313/01/202531/07/2025
PuketuruaArapuni17213/01/202531/07/2025
RotoitiRotoiti 219424/03/202531/07/2025
TaradaleBreckenridge Rd1024/11/202431/07/2025
WaitakereWaitakere Fringe South19617/02/202531/07/2025
WhangamataWhiritoa57313/01/202531/07/2025
WhangamataOputere10221/04/202531/07/2025
HastingsPakipaki4216/09/202431/08/2025
Okere FallsMourea21821/04/202531/08/2025
OnerahiParua Bay28510/02/202531/08/2025
RotomaRotoma24124/02/202531/08/2025
RotomaPongakawa Valley Road8931/03/202531/08/2025
TapuTe Mata20110/03/202531/08/2025
TaupoWaitahanui23317/03/202531/08/2025
WhangamataOnemana38131/03/202531/08/2025

*Due to size of Hamurana build area, this is being released in a staged manner over May, June and July to manage provisioning schedules and expectations. Expressions of interest received in this area have been informed.

What's next

The above table will be updated as the programme progresses and we will notify you when this happens as part of the standard service provider communications email update process. 

To receive address lists for premises that will be ready for connect soon, please contact your Chorus account team.

Keep up to date with the Chorus fibre network extension.

Project team

Paul Dobinson

Project Lead

Akash Nellore

Account Manager

Luke Henshall

Communications Manager