Network Capacity Update - September
Network Capacity update 1: 10 September 2015
This fortnightly report aims to assist you in your investigations around end-customers experiencing unsatisfactory broadband performance. The report highlights those links within the Chorus aggregation network that have experienced peak utilisation at or above 90 percent in the last two week period.
These are the links within the Regional Ethernet Network (REN) where peak utilisation has exceeded 90% capacity within the last two week period with potential implications for your customers' video streaming experience.
Aggregation network high utilisation links
Recently fixed
For more information and previous month's reports go to the Network Capacity section on our website.